Project Overview: Six-Phase Mechanical & Hydraulic Lifting and Sliding Parking Systems (Over 900 Total Parking Spaces Delivered)
Dalian Software Park Ascendas Park—jointly developed by Singapore’s Ascendas Group and Dalian Software Park Co., Ltd.—spans 35 hectares with a total investment of USD 200 million. Featuring seven office buildings and an integrated commercial and leisure center across 612,000 square meters of floor area, the campus experiences a daily traffic flow of roughly 3,000 vehicles.
As surface parking spaces fell short of peak commuting demand, roadside congestion and irregular parking created traffic bottlenecks and safety hazards across the campus. Building multi-level automated mechanical parking systems within constrained land footprints proved to be the most practical solution.
Since initiating parking expansion tenders in 2017, Ascendas Park has launched seven project phases. Following operational limitations in the initial phase constructed by another supplier, campus management conducted an extensive evaluation of mechanical parking equipment manufacturers. Selected for our site-specific engineering layouts, reliable equipment performance, and dedicated on-site maintenance team, our company has delivered six consecutive project phases across five system configurations since 2018, bringing over 900 mechanical parking spaces into daily operation.
Completion Date: January 2018
Equipment Type: Two-level lifting and sliding mechanical parking system
Capacity: 27 parking spaces
Completion Date: July 2018
Equipment Type: Four-level and five-level lifting and sliding mechanical parking systems
Capacity: 161 parking spaces
Completion Date: August 2019
Equipment Type: Five-level and six-level lifting and sliding mechanical parking systems
Capacity: 152 parking spaces
Completion Date: September 2020
Equipment Type: Two-level lifting and sliding mechanical parking system
Capacity: 158 parking spaces
Completion Date: May 2021
Equipment Type: Three-level lifting and sliding mechanical parking system
Capacity: 158 parking spaces
Engineering Highlight: Guided by our space-maximizing design approach, our engineers utilized the natural hillside slope in Zone E to create a semi-underground, open-structure layout that maximizes vehicle capacity while maintaining smooth entry and exit flow.
Completion Date: April 2022
Equipment Type: Six-level hydraulically driven lifting and sliding mechanical parking system
Capacity: 250 parking spaces
Built against a steep hillside north of Building No. 1, the 250-space garage adopts a stepped structural layout tailored to the terrain, with exterior cladding coordinated to match the main office building.
High-Speed Hydraulic Lifting: Powered by an 11-kW hydraulic pump station motor, the system achieves a lifting and lowering speed of up to 18 m/min—approximately 2 to 3 times faster than conventional motor-driven systems—significantly reducing driver waiting times during peak hours.
Patented Anti-Fall Safety Protection: Equipped with our patented mechanical anti-fall safety device, the structure is engineered for dependable mechanical protection, low maintenance requirements, and stable day-to-day operation.
| |
Beyond equipment manufacturing and installation, we operate a structured after-sales and preventive maintenance system designed to balance operational safety with cost efficiency. Our stationed technicians conduct daily equipment inspections, provide safety operation training for property staff and drivers, and assist with peak-hour parking guidance. These operations have earned positive recognition from local special equipment inspection authorities, quality supervision agencies, and campus tenants.
Through six phases of continuous delivery, these automated parking facilities have eased campus parking shortages, reduced surrounding road congestion, and provided a clean, reliable parking environment for employees and visitors.